The next two weeks will see a number of works happening in Sections 1,2 and 5. Find out more about each below. Sections 1&2 – A660 Otley Road and Headingley Lane from Shaw Lane to Richmond Av

A660 Leeds

The next two weeks will see a number of works happening in Sections 1,2 and 5. Find out more about each below. 

Sections 1&2 – A660 Otley Road and Headingley Lane from Shaw Lane to Richmond Avenue

  • Surfacing works completed on inbound section of cycle track
  • Works will continue outside of Headingley Central (Arndale Centre)
  • Night works have begun between St Michael's Road and Shaw Lane on the outbound side of the road, with works taking place from 7pm-6am, with noisy works being undertaken prior to 11pm.
  • Paving works fully completed at St Michael's Road, with event held there for Remembrance Sunday.

Section 5 – Hyde Park Corner 

  • Works continuing on Woodhouse Street repaving the old footway, and creating a new, large community area.
  • Works continuing at the corner of Hyde Park Road and A660 to complete traffic signals and pedestrian crossing upgrades.

Thank you for your continued patience during the works. You can contact us at any time at connectingleeds@leeds.gov.uk. 

Further information about the scheme can be found here.