2025 Sunset Pines Phase 3A (Hemlock Dr.)
About
Phase 3A of the multi-year stormwater and paving improvements to Sunset Pines are underway again in 2025. This year's portion of the project is the first section of Hemlock Drive and includes water, stormwater, curbing, and paving.
Stay Informed
Get notified on upcoming engagements and the latest project related news.
Contractor's Schedule
Suburban line relocation
1 week
Stormwater installation by Big Rock
2 weeks
Topsoil restoration
1 week