Paving Next Week (August 23-25)
Paving along E Bald Eagle and Race Street will occur August 23 to August 25
As long as the weather cooperates, Big Rock Paving plans to be on site next week to complete the CDBG funded paving project along E Bald Eagle Street and Race Street. The contractor plans to mill both streets on Wednesday, August 23, complete base repairs and final prepwork on Thursday, August 24, and complete overlaying/sealing of both streets on Friday, August 25.
If there are any changes to this schedule, another alert will be sent. Please make arrangements for off street parking during this time period and expect traffic delays.
Please reach out to the Lock Haven City Planning Office at 570-893-5903 or aroberts@lockhavenpa.gov if you have any questions or concerns.