4. Work underway

Construction works are underway. The works are organised in phases with public realm works at Waldegrave, Vernon and Burghley Road starting first.

1. Purpose of the project

Next steps

Public realm improvements - Phase 1

The proposed Phase 1 works aim to create a continuous crossing along the northern side of Turnpike Lane, enhancing walkability and accessibility, particularly for people with disabilities and those with pushchairs. 

 New space for street greenery (Burghley, and Waldegrave Road junctions) and new cycle parking (Vernon and Waldegrave Road junctions) will be installed contributing to the key project objectives of enhancing the visual appearance of the street and encouraging active travel. 

 As part of the project’s vision, a unique visual identity and wayfinding has been designed specifically for Turnpike Lane. This identity is woven into the public realm improvements through engraved artwork set into granite slabs at key locations, guiding people walking along the street and reinforcing the Turnpike Lane distinctive character.

  • March 2025- starting construction and delivery of Phase 1 public realm works including:
    • Waldegrave Road junctions starting in March 2025
    • Burghley Road starting in April 2025
    • Vernon Road starting in May 2025 

Phase 1 of the Turnpike Lane Improvement Plan have now been completed.

Pictures below are from 5 November.

Read the latest news here - https://turnpikelane.commonplace.is/en-GB/news/phase-1-of-the-public-realm-works-completed

Public realm improvements - Phase 2

The proposed Phase 2 works include improvements to the Alexandra Road junction. 

Alexandra Road proposals will create new areas of public realm to bring more life to the street by providing spaces to host a range of activities including seasonal events, al-fresco dining, live music and other cultural events.

The estimated start of construction of Phase 2 public realm works is scheduled for Spring 2027, subject to TfL approval. 

Public realm improvements - Phase 3

The public realm works may include a third phase, which proposes the installation of a new signalised crossing in the middle of Turnpike Lane.

This new crossing would improve safety for pedestrians, particularly those crossing from nearby bus stops to Harringay Passage. The proposals also include a new pavement build-out featuring rain gardens and cycle stands, with the potential to accommodate EV charging points in the future.

Delivery of Phase 3 is subject to approval from TfL and the availability of funding.

Shopfront improvements

The works are light-touch interventions designed to refresh and enhance the appearance of the shopfronts. Proposed works include a new fascia board, projection sign, awning, and redecoration of window frames and pilasters. The shops that will take part in the programme are Sabha Jewellers, Saree Emporium, Shania Supermarket and Paradise Halal Butchers.  

  • January 2025 to July 2025 – tender period
  • August 2025 – appointment of main contractor
  • November 2025 – starting construction and delivery of shopfront improvements 
  • February 2026 – estimated completion of shopfront improvements

Read the latest news here - https://turnpikelane.commonplace.is/en-GB/news/shopfront-improvement-works-underway