External Major Works programme
Information on the major works programme which is being undertaken to all blocks (other than Rochford and Martlesham)
Broadwater Farm Estate
External Major Works programme
DCK Construction has been awarded the contract to undertake this 18-month programme of external major works.
These works started in October 2025 and should be completed by October 2027.
The programme includes the following:
repairs and refurbishment of the structural concrete
new liquid coating for all residential balconies and communal walkways
new lighting in the undercroft
repair or replace the undercroft drainage
new flooring for all communal areas

The major works programme is planned by the required works. That’s why you may notice contractors working on different buildings at the same time, as work is phased across the estate to help keep the programme moving efficiently and minimise delays.
This phased approach helps keep the programme on track by:
- making efficient use of specialist teams
- allowing different activities to run simultaneously
- preparing scaffolding and access arrangements in advance
- minimising delays caused by hidden defects, material shortages or bad weather
DCK will write to each household letting residents know exactly when work on their building will start.
Upcoming planned schedule of works
The external major works repairs and improvements works have continued to progress well across the estate this month with several key activities completed.
Works completed in October included liquid coating and waterproofing works, communal flooring and scaffolding removal from Debden block (along Freedom Road).
Starting from Monday 2 November works will include:
- liquid coating and waterproofing to private balconies
- external wall painting, pigeon protection and pipework maintenance
- external timber balustrade replacement
- internal floor vinyl replacement and tiling of communal lobbies
- sandblasting and concrete repairs
Letters and notices have now been issued to affected residents. If there are any changes to the works schedule DCK will inform residents directly. Please also pay attention to all communal notices and signs which provide more information on the works happening in specific locations.
Select the drop boxes below for more information on each area of improvement happening in September.
Scaffolding remains in place at all blocks (other than at Debden block (along Freedom Road) for stage two of the external works - exterior painting and redecoration.
If you have any questions, please contact DCK’s Resident Liaison Officer, Andrei Capinus on 07463 633 467.
November 2026 - planned works
Click next to view current parking bay suspensions on the estate and scaffolding removal schedule.
Page updated: Thursday, 29 October 2026.
Current parking bay suspensions on the estate
The below tables provide a list of blocks, current parking suspensions and upcoming parking suspensions.
Croydon
| Suspension start date | Suspension end date | Number of bays |
| 9 October 2026 | 6 November 2026 | 26 |
| 23 October 2026 | 2 November 2026 | 8 |
Debden
| Suspension start date | Suspension end date | Number of bays |
| 23 October 2026 | 26 November 2026 | 32 |
Stapleford
| Suspension start date | Suspension end date | Number of bays |
| 30 October 2026 | 20 November | 20 |
Scaffolding removal schedule
Planned scaffolding removal dates:
Location | Planned removal date |
Freedom Road (Debden only) | From Thursday 1 October 2026 - complete |
Debden | mid-January 2027 |
Stapleford | mid-March 2027 |
Manston | late-March 2027 |
Lympne | mid-May 2027 |
Hawkinge | late-May 2027 |
Hornchurch | mid-July 2027 |
Croydon | late-July 2027 |
If these dates change significantly, DCK will contact any affected residents directly.
Click next to view a photo gallery on the ongoing works.
Page updated: Thursday, 29 October 2026.
Photo gallery - ongoing works
Click next to find out about what's involved with programme specific works including:
- flooring works
- repairs and redecoration in the the undercroft car park spaces
- sandblasting works
- balcony clearance
Page updated: Thursday, 29 October 2026.
Programme specific information
Click next to view and download additional documents, including:
- answers to Frequently answered questions (FAQs)
- Broadwater Farm's parking exemption request form
- copies of resident correspondence
Page updated: Thursday, 29 October 2026.
Read our Frequently Asked Questions (FAQs) information sheets
If you have any questions, please contact DCK’s Resident Liaison Officer, Andrei Capinus on 07463 633 467.
Page updated: Thursday, 29 October 2026.
Discover more

Broadwater Farm heat network: metering, billing and tariff information
Keeping your heating and hot water service accurate and affordable.

Broadwater Farm New Homes Allocations
Learn more about how the new homes on Broadwater Farm are prioritised and allocated, including Right to Return residents and the Neighbourhood Moves Scheme.

Broadwater Farm Garden Terraces
Find out more about all the community garden terraces on Broadwater Farm.

Broadwater Farm community engagement
Get involved in community projects and activities happening on the Broadwater Farm Estate.

New fire and resident signage
We are renewing the fire and resident signage to the internal communal areas in the blocks. Learn more about how this could impact you.

Broadwater Farm priorities
Broadwater Farm resident priorities – what you’ve told us

Phase 1 - new homes construction, Frequently Asked Questions
Phase 1 - new homes construction: Answers to Frequently Asked Questions (FAQs)

Broadwater Farm outdoor Bar Park
We’re working with community partners Raza Sana looking at new ways to activate the greenspace on Broadwater Farm Estate.

School artwork hoarding project
How the children from Broadwaters’ Inclusive Learning Community helped us brighten up the hoardings on Phase 1 new homes construction site.
Stay Informed
Follow our projects to get notified of upcoming engagements and the latest project related news.