UK Power Networks recommence electrical cabling relocation works at Tangmere – January 2026

UK Power Networks (UKPN) will recommence cabling relocation works on the former Tangmere site from Monday 5 January 2026. We’re sharing this update to give you as much notice as possible about these w

Broadwater Farm Estate

UK Power Networks (UKPN) will recommence cabling relocation works on the former Tangmere site from Monday 5 January 2026. We’re sharing this update to give you as much notice as possible about these works and any potential impact to residents. 

These works are a continuation of those started earlier this year. The main works period is planned to run from Monday 5 January to early March 2026. UKPN will issue official notices to residents regarding road closures and power outages once dates and times are confirmed.

Here’s a general outline of the works with some key dates:

Week commencing Monday 5 January 2026

  • Works commence on site: Monday 5 January 
  • Willan Road pedestrian footpath closed: Monday 8 January to Sunday 14 January. The road will remain open to vehicles. 
  • Electrical power outage on Willan Road: Friday 9 January
    This will mainly impact communal services such as street lighting, but UKPN will contact any impacted residents before works begin. 

Week commencing Monday 22 January 2026 

  • Works start on Freedom Road: Sunday 25 January
    There will be traffic diversions in place during these works – more information on this in the new year 
  • Avenue Road closure: Monday 26 January (one day) - residents will not be able to exit the estate from this end of Gloucester during this closure. 

Gloucester Road closures 

Gloucester Road will be closed to traffic from 9am to 12pm closed on: 

  • Friday 2 February 
  • Saturday 3 February 
  • Saturday 10 February  

The bus service will be diverted during these times. 

Electrical power cut to Kenley and two other blocks 

There will be a one-day electrical power cut affecting Kenley and two other blocks in the new year. UKPN will contact impacted residents directly once the dates are confirmed. 

An electrical power cut means there will be no electrical supply to all homes and communal spaces in these blocks for a period while works are carried out. We are exploring options to provide a warm space in the community centre during these power outages. We’ll provide more information on this in the new year. 

Additional Information 

  • Vehicle removal enforcement 

Vehicles left in suspended bays or on roads marked for temporary closures will be moved to the car pound. Residents will be responsible for retrieval and any charges. Learn more about how to reclaim your vehicle on our website. 

Any questions
Please contact Chris White from UKPN at Chris.White2@ukpowernetworks.co.uk or email the Broadwater Farm Project team at bwf@haringey.gov.uk

Visit the improvement programme - works update page for all the latest information on works happening across the estate.