The Colour Way

The Colour Way

Improving the Park View Road underpass between Tottenham Hale and the Lee Valley Regional Park into a safer, more accessible and engaging route.

Find out more about the completed project below.

About the project

Email

Project History

After detailed designs were developed in Spring 2022, further site investigations were conducted from Summer 2022 to Summer 2023 to address drainage and water leakage issues. The designs were refined to include improved drainage and repairs to water leaks within the underpass. These designs were shared with Network Rail and London Underground in Autumn 2023 to secure their consent for the structural works.

Project Update

The Council's works on the underpass began on 17 June 2024 and were completed within the 22-week programme by mid-November 2024. Network Rail then carried out repairs to the concrete ceilings within the underpass, causing a brief delay in reopening the route to the public.

All physical works were completed by early December, and the underpass was reopened on 6 December 2024.

Improving green and open spaces is a key part of our placemaking strategy in Tottenham Hale. The Colour Way project is a significant step towards creating a network of enhanced open spaces and green pedestrian links in our area.

We are thrilled to have collaborated with local artist Albert Agwa from Bud Studio on the development and installation of artwork along the route. Albert, who has a passion for the creative arts, worked with local young people to create murals that reflect Tottenham's diverse communities and environments.

Find out more

The entrance to the Underpass

Background to the Colour Way project

Find out more about the project and next steps.

Posted:
Read More
ruk1g3t73difucpuqwqa.jpg

Frequently Asked Questions

Frequently asked questions from the local community. We will keep these updated throughout the works.

Posted:
Read More
Mock-up of artwork under Watermead Way flyover
Closed

Artwork proposals

Final proposed public artworks.

Project:Parkview Underpass
Proposed improved access to the Underpass
Closed

Physical improvements [survey closed]

A survey on the proposed physical improvements to the underpass and its approaches. This has now been completed.

Project:Parkview Underpass

News

12 items
Children riding bikes through into the Underpass

Join our celebration event on 22nd February!

We are celebrating the completion of the Colour Way project with a programme of exciting activities on Saturday 22nd February!Come and join us for family-friendly art activities, a guided nature walk

Posted:
View Update
sbocxvedsfgf9ibxxyyj.jpg

The Colour Way Project is complete! Join us for a festive cycle

Hi there!The Colour Way Project is now complete.Park View Road underpass has been transformed into a safer, more accessible, and vibrant route for pedestrians and cyclists!What's New?Stunning new

Posted:
View Update
The new raised wildflower planting bed viewed from Park View Road

Underpass re-opens on 6th December!

We are pleased to announce that the Underpass will re-open on Friday 6th December 2024. This follows confirmation from Network Rail that their ceiling repairs are now complete.Over the last few weeks,

Posted:
View Update
A view of the western entrance to the Underpass showing new shared use paving and new rows of drainage channels.

Works Update 3: Delay to re-opening of Underpass

The Council completed its improvements to the Underpass and its approaches on time in early November.Since then, Network Rail have been undertaking minor works to the Underpass ceiling to repair the c

Posted:
View Update
View of the completed works at the Park View Road entrance with new steps leading down to the Underpass.

Works Update 2: Underpass re-opening soon!

The improvements to the Park View Underpass have been progressing well over the summer, and are on track to be completed on time at the beginning of November!This means that as the winter nights draw

Posted:
View Update
View of the newly re-surfaced footway and cycle lane with new drains installed

Works Update 1: The Colour Way is taking shape!

The Colour Way is starting to take shape at the Park View Underpass as construction works progress rapidly over the summer.After kicking off on 17th June 2024, work on the Tottenham Marshes side has n

Posted:
View Update
A black cat chilling out on a car roof in front of the Underpass

Park View Underpass closes for the summer

Works are now underway on the Colour Way project to improve the Park View Underpass!This marks the start of a comprehensive project to improve the Underpass and its approaches, including repairs to dr

Posted:
View Update
Residents visiting the project exhibition

Community event celebrates the start of The Colour Way Project

Saturday 8th June saw a colourful community event to celebrate the start of construction on the Park View Underpass improvement project. Residents old and new attended the event in Down Lane Park

Posted:
View Update
Common blue butterflies

Nature walk, photo exhibition and art activities confirmed for 8th June event!

An exciting set of activities has been confirmed for the celebration event on 8th June to mark the start of construction works for The Colour Way, the project to revitalise the Park View Underpass. &n

Posted:
View Update
A view of the western entrance of the Underpass with new steps, shared paving and artwork

Join us on 8th June to celebrate the start of The Colour Way works!

Construction works on the exciting Colour Way project to revitalise the Park View Road Underpass kick off on 10th June 2024!The project will create colourful and vibrant artworks along the paths leadi

Posted:
View Update

Update on the Colour Way - May 23

Thank you to everyone who provided feedback on the Colour Way project to improve the Park View Underpass.Since community engagement on our plans in late 2021, we have been undertaking further investig

Posted:
View Update

Thank you for your participation: Consultation outcomes and what’s planned next

Update on consultation outcomes and what's planned nextThank you to everyone who gave feedback on plans to improve Park View Road Underpass through the Colour Way Project. The project aims to tran

Posted:
View Update

About the Colour Way

The Park View Road underpass is a vital link between Tottenham Hale and the Lee Valley Regional Park. The Colour Way project has transformed this underpass into a safer, more accessible, and engaging route for pedestrians and cyclists through physical improvements and vibrant artwork.

This project has introduced colorful and dynamic artworks along the paths leading to the underpass and delivered physical enhancements such as new paving, new stepped access from Park View Road, improved lighting in the underpass, tiling repairs, and soft landscaping. Additionally, we have upgraded the drainage system to minimize flooding after heavy rainfall. These improvements are supported by more active maintenance of the area, in collaboration with the community and partners.

Albert's artwork installation took place from 2 to 16 December, completing the Colour Way project.

Meet the team

Haringey Council
Haringey Council

Haringey is our home, and we are proud of it. We are ambitious for Haringey’s future and have great ambitions for the people who live here.

The council will work in partnership with Homes for Haringey, our partners, as well as the existing local residents and community to improve the local area.
We are committed to addressing the disparities within our borough and will ensure we create a fairer and more equal community. Any new development must be more than shiny new buildings, it must bring new opportunities for local people and ensure the existing community can participate and benefit from the investment in their neighbourhood.

We are eager to work with partners who share our vision; to collectively, with local people, improve our borough in a way that ensures our whole community not only can live a good life, but thrive.

Read Haringey Council privacy policy