Improvement works programme – September 2026 update
This update gives information on all the current improvements works happening on the estate. New homes Phase 1 new homes - Freshwater CourtFreshwater Court is now complete. Phase 2 form
Broadwater Farm Estate
This update gives information on all the current improvements works happening on the estate.
New homes
- Phase 1 new homes - Freshwater Court
Freshwater Court is now complete.
- Phase 2 former Tangmere site
Works on site are progressing well, with the external framework of the townhouses taking shape and significant progress visible across the development.
We are holding a meet the contractor and construction information event in the community centre in the autumn. Dates and timings will be shared via the Broadwater Farm Engagement Hub soon.
- Northolt and Stapleford North
Due to an administrative issue relating to the contracts, the demolition works on the Northolt and Stapleford North buildings, which were expected to start on 1 September, have been delayed.
Residents will receive a letter from our contractors once a new date is agreed to give you notice of start dates, explain the planned works and what to expect and confirm any road closure dates.
Refurbishment
- Major works programme
Planned works for September include replacing communal flooring in Hawkinge and Lympne blocks, painting works in the Debden undercroft car park, painting and sandblasting works in Hawkinge undercroft car park and sandblasting resident balconies in Croydon block.
DCK has sent all affected residents letters advising them of start dates and timings.
- Pilot refurbishment – Rochford and Martlesham
Planning consent was granted in January 2026. We are now working with consultants and contractors to meet Building Safety Regulator requirements. The project remains on track to start in January.
Public space
- Debden pilot undercroft project
We are commissioning local artists to support co-design workshops with residents for the artwork to the new Debden walkway. More information on upcoming workshops will be shared via the Broadwater Farm Engagement Hub soon.
- Broadwater Farm Community Centre
The reception floor tiles are currently being replaced. We expect these works to be completed by the end of September. The reception can still be used with clear walkways and signage displayed.
Learn more about the full programme of improvements
Visit the improvement programme works update page to learn more about the above improvements.
View the project timeline for an overview of each stage of the programme.
You can also visit the Broadwater Farm page on Haringey's website to learn more about:
Stay Informed
Follow our projects to get notified of upcoming engagements and the latest project related news.