p6zroysydiooftk6hfoi.jpg
Project

Construction underway

Progress being made on the Civic Centre

History of Civic Centre

Construction & Progress Update

April–Feb 2026

The transformation of Haringey’s Civic Centre is officially underway. Since construction began in April, the site has seen steady progress, with major milestones reached and strong community engagement throughout. This update walks through the journey so far — from early groundwork to the rising annex and everything in between.

April: Laying the Groundwork

Construction officially kicked off on 8 April 2025, with contractor Sisk mobilising on site. The team took advantage of the quieter Easter holiday period to minimise disruption to the local community, particularly around Trinity Road, where temporary traffic measures were introduced.

Initial works focused on clearing the site and preparing it for heavy machinery. This included:

  • Removing old hoarding and installing new site boundaries
  • Clearing muck and debris from the area
  • Installing a piling mat to support safe movement of equipment
  • Beginning excavation for an attenuation tank in the old Civic Centre car park — a key feature to manage rainwater and reduce flood risk

These early steps laid the foundation for both the restoration of the existing Civic Centre and the construction of the new annex.

May: Breaking Ground

May marked a major milestone with the official groundbreaking ceremony. The event brought together Wood Green MP Bambos Charalambous, Haringey councillors past and present, senior council officers, and representatives from Sisk to celebrate the start of the Civic Centre’s transformation.

Alongside the ceremonial moment, real progress was happening on site:

  • The crane base was installed in the courtyard and car park
  • Piling works for the annex foundations were completed
  • A new attenuation tank was installed in the Bounds Green Road service area
  • Scaffolding began to rise around the Civic Centre, preparing the building for roof works and façade repairs

Internally, clearance and waterproofing works began in the Civic Centre basement, setting the stage for future refurbishment.

June: Building Momentum

With the groundwork complete, June saw the project shift into structural and technical development.

Key updates included:

  • Continued scaffolding installation, including a temporary roof to protect the building from weather
  • Start of heritage joinery removal inside the Civic Centre, preserving original features while making space for modern upgrades
  • Basement demolition progressed, including the removal of walls, plinths, and outdated plant
  • Drainage adaptations began, improving the building’s resilience and preparing for new utility connections

Externally, construction of the new substation commenced in the Bounds Green service area. This will eventually power both the restored Civic Centre and the annex.

Sisk also began outreach to local employment groups, with plans to recruit from within Haringey as the project progresses. More information on job opportunities is expected later in the year.

July: Structures Take Shape

By July, the Civic Centre site had visibly transformed. The most striking change was the arrival of the tower crane, now a prominent feature behind St Michael’s Church. It will remain on site throughout the build, supporting the lifting and distribution of materials.

Other major developments included:

  • Scaffolding completed around the building exterior
  • Attenuation tanks installed at both the front and rear of the Civic Centre
  • Drainage works continued in the courtyard and car park
  • Waterproofing works began at ground level
  • Service duct installation started between the buildings

The annex construction moved into its next phase, with the ground floor taking shape and preparations underway for the first-floor columns and core walls. Foundations for the link building also began, connecting the annex to the Civic Centre.

Inside the Civic Centre, works continued on the roof and façade, while foul drainage systems were installed to manage wastewater.

August: Foundations Strengthen

August marked another month of steady progress at the Civic Centre site, with key groundwork and structural milestones achieved. Here's a summary of the latest activity:

  • Attenuation tank 4 installed to help reduce future flood risk
  • Scaffolding now surrounds the building for roof and facade works
  • Substation foundations laid near Bounds Green Road
  • Service ducts installed in the courtyard for future utilities
  • Ground floor slab completed
  • Internal demolition underway with heritage protection
  • Annex link poured and columns erected
  • Mock-up facade panel built to preview final finish
  • Next steps: floor pours, drainage installation, roof and facade preparation.

September: further foundations

Scaffolding now surrounds the building, with the temporary roof nearing completion. The new substation near Bounds Green Road has been built, and service ducts in the courtyard are now installed to support drainage.

Inside, demolition works are ongoing across multiple floors. The link between the Annex and the main building is progressing, with columns and slabs being poured. In the Annex, stairwells and lift shafts are now in place, and a cladding panel mock-up has been completed.

October:

  • Scaffolding has reached its final phase, now being erected around the west wing (Committee Rooms).
  • The new substation roof is complete, with door installations underway.
  • Internal demolition continues across the basement and upper floors.
  • Temporary formwork is being installed in the link building between the annex and main Civic Centre to support concrete pours.
  • The core structure of the annex is now complete on the first floor.
  • A hoist has been installed in the main Civic Centre to support material movement.
  • Concrete pouring has begun on Level 2 of the annex, with the second half to follow shortly.

November: Reaching New Heights

November has been a milestone month at the Civic Centre site, with major structural and facade works progressing. Here’s what’s been happening:

  • Final concrete pours for the annexe roof are underway, marking the building’s highest point
  • Link building concrete frame completed with roof slab poured
  • Substation construction finished on Bounds Green Road side
  • Lift shaft openings progressing in the Civic building for future services
  • Facade works started on the annexe with steel framing system (SFS) installation
  • Internal scaffolding erected in the main chamber for safe access
  • Final attenuation tank installed to improve site drainage

Next steps:

  • Complete topping out of the annexe
  • Continue facade works and drainage runs
  • Begin electrical and plumbing installations
  • Prepare upstands for Civic building facade and carry out soffit repairs

Feb 2026: Topping Out: A Major Step in Restoring the Civic Centre


  • A topping out ceremony was held on the roof of the new annexe to mark the project reaching its highest point
  • The tradition – historically used to ward off evil spirits – recognises a key milestone in the redevelopment
  • The Leader of Haringey Council and the Mayor joined councillors, the project team, contractors Sisk and local apprentices for the celebration
  • Sustainability and energy efficiency remain central to the scheme, which is on track for completion in late 2026
  • The refurbished Grade II listed Civic Centre will support up to 900 staff in high‑quality workspaces, with restored civic areas open for community use
  • The redevelopment aligns with preparations for Haringey becoming London Borough of Culture in 2027

History and design highlights

  • First listed by English Heritage in 2018, the Civic Centre has played a defining role in Haringey’s political and civic life since 1958
  • Historic figures connected to the building include Bernie Grant, Joyce Butler MP and George Michael
  • Residents have responded positively through multiple engagement events
  • The scheme includes a new central courtyard, extensive landscaping and major energy‑efficiency upgrades such as full insulation and solar panels
  • Restoring the Civic Centre offers the best value option for the council’s long‑term accommodation needs
  • The project also enables alternative uses for other council buildings in Wood Green, supporting ongoing investment in the area