Photo of estate from Lordship Rec - showing crane working on site
Project

External Major Works programme

Information on the major works programme which is being undertaken to all blocks (other than Rochford and Martlesham)

Broadwater Farm Estate

External Major Works programme

DCK Construction has been awarded the contract to undertake this 18-month programme of external major works. 

These works started in October 2025 and should be completed by October 2027.  

The programme includes the following:  

  • repairs and refurbishment of the structural concrete  

  • new liquid coating for all residential balconies and communal walkways  

  • new lighting in the undercroft  

  • repair or replace the undercroft drainage  

  • new flooring for all communal areas 

Photo of the estate from Lordhip Rec with a crane on site

The major works programme is planned by the required works. That’s why you may notice contractors working on different buildings at the same time, as work is phased across the estate to help keep the programme moving efficiently and minimise delays.

This phased approach helps keep the programme on track by:

  • making efficient use of specialist teams
  • allowing different activities to run simultaneously
  • preparing scaffolding and access arrangements in advance
  • minimising delays caused by hidden defects, material shortages or bad weather

DCK will write to each household letting residents know exactly when work on their building will start.

Upcoming planned schedule of works

The external major works repairs and improvements works have continued to progress well across the estate this month with several key activities completed.

Works completed in October included liquid coating and waterproofing works, communal flooring and scaffolding removal from Debden block (along Freedom Road). 

Starting from Monday 2 November works will include: 

  • liquid coating and waterproofing to private balconies
  • external wall painting, pigeon protection and pipework maintenance
  • external timber balustrade replacement
  • internal floor vinyl replacement and tiling of communal lobbies
  • sandblasting and concrete repairs

Letters and notices have now been issued to affected residents. If there are any changes to the works schedule DCK will inform residents directly. Please also pay attention to all communal notices and signs which provide more information on the works happening in specific locations.

Select the drop boxes below for more information on each area of improvement happening in September.

Scaffolding remains in place at all blocks (other than at Debden block (along Freedom Road) for stage two of the external works - exterior painting and redecoration. 

If you have any questions, please contact DCK’s Resident Liaison Officer, Andrei Capinus on 07463 633 467. 

November 2026 - planned works

Click next to view current parking bay suspensions on the estate and scaffolding removal schedule.

Page updated: Thursday, 29 October 2026.

Current parking bay suspensions on the estate

The below tables provide a list of blocks, current parking suspensions and upcoming parking suspensions.  

Croydon

Suspension start date
Suspension end date
Number of bays
9 October 20266 November 202626
23 October 20262 November 20268

Debden

Suspension start date
Suspension end date
Number of bays
23 October 202626 November 202632

Stapleford

Suspension start dateSuspension end dateNumber of bays
30 October 202620 November20

Scaffolding removal schedule

Planned scaffolding removal dates:

Location
Planned removal date
Freedom Road (Debden only)
From Thursday 1 October 2026 - complete
Debden
mid-January 2027
Stapleford
mid-March 2027
Manston
late-March 2027
Lympne
mid-May 2027
Hawkinge
late-May 2027
Hornchurch
mid-July 2027
Croydon
late-July 2027

If these dates change significantly, DCK will contact any affected residents directly.

Click next to view a photo gallery on the ongoing works.

Page updated: Thursday, 29 October 2026.

Photo gallery - ongoing works

Click next to find out about what's involved with  programme specific works including:

  • flooring works
  • repairs and redecoration in the the undercroft car park spaces
  • sandblasting works
  • balcony clearance

Page updated: Thursday, 29 October 2026.

Programme specific information

Click next to view and download additional documents, including:

  • answers to Frequently answered questions (FAQs)
  • Broadwater Farm's parking exemption request form
  • copies of resident correspondence

Page updated: Thursday, 29 October 2026.

Read our Frequently Asked Questions (FAQs) information sheets

If you have any questions, please contact DCK’s Resident Liaison Officer, Andrei Capinus on 07463 633 467.  

Page updated: Thursday, 29 October 2026.