Frequently Asked Questions

Frequently asked questions from the local community. We will keep these updated throughout the works.

Background to the Colour Way project

Frequently Asked Questions

Frequently Asked Questions 

We will be updating this page on a regular basis to support residents and the community with any queries they have about The Colour Way project.

How will the artwork be protected from graffiti damage?

We have a maintenance agreement with the artist to repair any damage caused to the artwork by vandalism. We also have our standard rapid response to offensive or racist graffiti. 

We have not used an anti-graffiti coating, as they generally enable graffiti to be cleaned more easily but do not prevent graffiti from adhering to surfaces. Anti-graffiti coatings can also be costly, and need to be re-applied regularly after they have been cleaned several times. We have chosen to invest in a local service by commissioning the artist to undertake regular maintenance. 

How can we report any damage or maintenance needs?

Residents and visitors can support the maintenance of the area by promptly reporting any graffiti, fly-tipping, damage to assets or maintenance needs using the Love Clean Streets app. Photos can be uploaded on the app to illustrate the problem. The app can be downloaded online.

Why does the artwork and improvements not extend further, the area is in dire need of improvements?

The artwork is an extensive piece of mural art over approximately 70 wall panels, extending from the walls around the base of the Watermead Way flyover next to Tottenham Marshes to the end of the screen walls opposite the Harris Academy sports facility. 

As there is a fixed budget for this project, the priority has been to address the flooding issues with repairs to existing broken drains and installation of new connections and drainage channels to minimise incidents of flooding after heavy rainfall. The re-surfacing and landscaping works focus on improvement within the Underpass and at both entrances, including removal of the retaining wall and railings at the end of Park View Rd and the installation of new steps to access the Underpass. 

I do not feel the images are representative of the area, why were these images chosen?

The artwork commission set out to explore the relationship between the urban and natural landscapes that meet in this location, using engagement with local young people to develop the artwork themes and images. 

The artist, Albert Agwa of Bud Studio, focussed on engaging young people from Tottenham with an interest in the creative industries, to provide them an opportunity to engage in the creative process and learn technical skills. The images were developed through workshops with the young people, and represents their experience and feelings about Tottenham. Many of the images represent the places that people experience in the Tottenham area, from where they live, important buildings and construction to the natural features and wildlife of the Lee Valley. 

How have you listened to our feedback around providing a safer route of travel for cyclists and pedestrians?

The Colour Way improvements will create a brighter, more attractive and better maintained route to attract more people to use the Underpass and to deter anti-social behaviour. We have listened to feedback about crime and perceptions of safety in the area. As a result, we installed a temporary mobile CCTV camera at the Tottenham Marshes approach to the Underpass and worked with the Community Payback team to remove unsightly and dangerous razor wire hanging over the boundary of the Millmead Industrial Estate. We are also exploring options for addressing the anti-social behaviour and rough sleeping that takes place in the gated space under the Watermead Way flyover on the Tottenham Marshes side. 

The area around the Underpass looks uncared for. What is being done to improve maintenance of the area? 

A maintenance and management plan has been developed for the wider area around the Underpass to provide a greater focus on stewardship. Existing levels of maintenance have been reviewed, and the Council is working to improve the effectiveness of maintenance and management activities. The Council also aims to work with partners and other local stakeholders to address issues that affect the area’s appearance and the experience of using the area.

What other routes can I take to the Marshes that provide accessibility? 

An alternative accessible route to the Marshes is to join Watermead Way at Burdock Road (south of Harris Academy) and to travel north to the next access gate to the Marshes at the base of the Tottenham Marshes Bridge (‘Carbuncle Passage Bridge’). Step free access to the Marshes is also available to the south, via the entrance gate to the Lee Valley Park at the junction of Ferry Lane and Millmead Road. Step-free access across the railway is also available at Northumberland Park station to the north, via access ramps at both entrances to the station.    

Will there still be step-free access for bicycles through the Underpass?

Yes, the existing step-free access for bicycles, wheelchairs and buggies will be retained at both entrances to the Underpass.  

What is the advantage of removing the vehicle barriers and adding steps at the western end (Park View Rd.)?

The introduction of new steps at the western side is intended to provide a clearer and more welcoming approach to the Underpass, and help people find their way to the Lee Valley.

Feedback from local engagement over the years has highlighted the lack of knowledge about this route to Tottenham Marshes. 

The removal of the existing unattractive vehicle barriers, and their replacement with new steps flanked by raised wildflower planters, will make the route more visible and welcoming. 

It will also increase 'passive surveillance' over the Underpass entrance, as the removal of the vehicle barrier and retaining wall will make the approach more open and less sheltered.   

When was the project delivered?

After receiving Network Rail and London Underground consent to work on the Underpass, the project works started on 17th June 2024 and was completed on be completed on 16th December 2024. 

Why did the works start in June, when there is high demand for access through the Underpass?  

Works at any time of the year in this location are likely to have an impact. For example, pushing the works back until the autumn would have shifted the disruption into the darker winter months making alternative routes less appealing for a range of users.

The drainage works also required drier weather, and the summer months provided longer operating hours. 

Why has the programme of works increased from 14 to 22 weeks?

We tried very hard to minimise the disruption from the works, from considering phasing of the works to exploring ways of getting access across the Marshes in order to make working on the eastern side easier and quicker. Unfortunately, none of these options proved practical or cost-effective. 

This meant that much of the work had to be done manually, as there was a risk to the railway of taking mechanical plant through the Underpass. This contributed to the extended works programme. However, we worked with the contractors to explore ways to shorten the programme, and to keep access available for as long as possible.

While the programme had to be extended from the planned 12-14 weeks to 22 weeks, the works included significant drainage improvements that were not originally planned. Instead of simple gully replacements, they now include repairs to sections of collapsed drains, new connections to Thames Water’s sewers, and the installation of new lateral slot drains across the entrance ramp.

Any further questions? Please email tottenhamregeneration@haringey.gov.uk

Discover more

The entrance to the Underpass

Background to the Colour Way project

Find out more about the project and next steps.

Posted:
Read More
Mock-up of artwork under Watermead Way flyover
Closed

Artwork proposals

Final proposed public artworks.

Project:Parkview Underpass
Proposed improved access to the Underpass
Closed

Physical improvements [survey closed]

A survey on the proposed physical improvements to the underpass and its approaches. This has now been completed.