External major works – works programme phasing explained

The external repairs and improvement works are being delivered over an 18-month planned programme. As the programme progresses, DCK start work on a new building before all works are completed on

Broadwater Farm Estate

The external repairs and improvement works are being delivered over an 18-month planned programme. 

As the programme progresses, DCK start work on a new building before all works are completed on the previous block. Without these programme overlaps, delays on one building could affect progress across the entire estate. 

This phased approach helps to ensure: 

Efficient use of contractors and resources - Different teams carry out different types of work. Rather than waiting for all works to be completed on one block, teams can move to the next building, helping to keep the programme on track. 

A shorter programme duration - Overlapping works allows multiple activities to take place at the same time, reducing the overall length of the programme. 

Smoother access arrangements - Scaffolding can be erected on the next building while works are still being completed on the previous one, ensuring the next phase is ready to begin when teams become available. 

Better management of risks and delays - Programme overlaps help minimise the impact of unexpected issues, such as:  

  • hidden defects 
  • material supply delays 
  • access issues 
  • Bad weather

That’s why you may notice contractors working on different buildings at the same time, as work is phased across the estate to help keep the programme moving efficiently and minimise delays. 

Programme update 

Visit the external major works programme page for the latest programme update. 