Major works update - Internal flooring and sandblasting works
This is an update on the next stages of the major works programme on the estate. Internal flooring works Lympne BlockThe next phase of flooring replacement works is planned to begin on the5t
Broadwater Farm Estate
This is an update on the next stages of the major works programme on the estate.
Internal flooring works
Lympne Block
The next phase of flooring replacement works is planned to begin on the5th floor at Lympne, starting week commencing Monday 27 April.
Debden Block
Flooring latex preparation and the installation of new tiles will take place in the rear entrance staircase, starting on Friday 1 May.
All residents directly affected by these works have already been notified.
Sandblasting works
Sandblasting works are scheduled to start on private residential balconies and in the undercroft car park area at Manton, beginning week commencing Monday 4 May.
All affected residents will receive a letter with further details today.
Need help or have questions?
Contact DCK’s Resident Liaison Officer, Andrei Capinus, on 07463 633 467,
or email the Broadwater Farm Project Team at bwf@haringey.gov.uk.