Construction
Project

Construction updates

Information on the works underway.

Penstock Tunnel

Construction works

IMPORTANT UPDATE

Penstock Tunnel temporary closure – 26 & 27 January

Penstock Tunnel will be closed on 26 and 27 January between 9:15am and 2:45pm to allow for the installation of new street furniture and artwork features.

Due to the limited space inside the tunnel and the use of large construction vehicles and equipment, the footway and cycleway beneath the tunnel will need to be temporarily closed during these works.

A signed diversion route will be in place throughout the closure.

Background 

Improvement works started at Penstock Tunnel week commencing 21 July 2025.

Improvement works to the tunnel included:

  • Improved lighting  
  • Improved drainage and new Sustainable Urban Drainage Systems  
  • Reconstruction and resurfacing of the shared footway and cycleway 
  • Soft Landscaping  
  • New street furniture  

A temporary closure of Penstock Tunnel started on Wednesday 23 July and the tunnel reopened on Monday 1 September. 

Project progress

Works within the tunnel completed to 1 September:

  • Network Rail/Amco Griffen drainage works completed
  • Granite sett, tactile, dished channel, segregation block, block paving and asphalting works completed within the tunnel and to West entrance to tunnel
  • Old lighting units & feeder pillar removed, disconnected. New tunnel lighting units and new feeder pillar installed to both walls

Works to the east entrance of tunnel completed to 1 September

  • Excavation and site clearance of existing planter and new land to be leased 
  • Dangerous branch removal
  • Rain garden excavated to formation level and drainage installed

Works within the tunnel completed to 30 September:

  • Footway reconstruction across scheme substantially complete (85%)
  • Raised planter and footpath in construction (Planting, play items, surfacing outstanding)
  • Western timber deck completed. Eastern timber deck substantially complete 

Works within the tunnel completed to 25 October:

  • Footway paving reconstruction complete
  • Raingarden kerbing works finished
  • Lighting columns installed at the tunnel approach
  • Fencing boundary works currently underway

Stay Informed

Follow our projects to get notified of upcoming engagements and the latest project related news.