Project

Ferry Lane Improvements

Proposal to improve Ferry Lane, a key east-west route through Tottenham Hale.

Projects underway in Tottenham Hale

Ferry Lane Improvements

Proposed Ferry Lane Improvements

In June 2025, Haringey Council granted permission to vary a planning condition attached to the 2014 planning permission for the redevelopment of Tottenham Hale Station. The proposals replace the requirement for a new footbridge linking Hale Village and Tottenham Hale Station with improvements to Ferry Lane instead.

Haringey Council have finalised the designs to upgrade the highway along Ferry Lane, with a focus on enhancing walking and cycling infrastructure. These improvements will make it safer and easier for residents, commuters and visitors to travel to and from Tottenham Hale Station.

The project will deliver the following specific infrastructure improvements:

  • Increased Footway Capacity: Widened footways across Ferry Lane bridge, delivered by narrowing the existing carriageway, with kerbs and pedestrian guardrails relocated to maximise available space for pedestrians.
  • Segregated Cycle Lanes: New cycle tracks along Ferry Lane that separate cyclists from vehicles, 
  • New Pedestrian Crossing: A new pedestrian crossing on the east arm of the bus station junction outside the station entrance, providing a direct route across Ferry Lane.
  • Improved Junction Layout: An upgraded crossing at the bus station junction, converting the western side from a staggered crossing layout to a straight through alignment to optimise pedestrian movement and safety.
  • Floating Bus Stop Upgrade: Upgrading the existing eastbound bus stop outside Hale Village to a floating bus stop layout, maintaining segregation between cyclists and traffic while buses pull in to pick up and set down passengers.
  • Community Safety Measures: Installation of 3 new (CCTV) cameras to enhance public safety.
  • Street Lighting Improvements: Provision of new and enhanced street lighting along Ferry Lane to improve safety and modernise lighting assets.
  • Public Realm (Art) Enhancement: Installation of new public street art to improve the local environment.
  • Dedicated Bus Lane: A dedicated left turn only bus lane on the approach to the bus station junction (westbound), reducing conflict points where vehicles currently merge.

Start of works

Construction works began on 17 August 2026 with the establishment of our secure site compound, site clearance, and setting out operations. The entire public realm scheme is expected to take approximately 11 months to complete, with final completion targeted for June 2027. Construction will progress along Ferry Lane in distinct phases outlined in the delivery programme below:

The delivery programme is broadly structured as follows:

When

Where

What

17 August to middle of September 2026

(Enabling Works)

Various locations along Ferry Lane and Harris Lebus Way

Setup of a secure site compound on Harris Lebus Way, on the highway near the bridge. Civil preparation works will follow ahead of traffic management phases. A night time carriageway closure will take place at the very end of this phase to amend road markings and install temporary safety barriers, enabling the next stages of construction.

Middle of September to late November 2026

(Phase 1)

Northeast side (by Hale Village) from Mill Mead Road junction towards bridge approach 

Footway reconstruction works on the northern side of the bridge, commencing at Mill Mead Road and progressing westwards towards Hale Village and the Bridge.

Late November 2026 to 20 December 2026

(Phase 2)

North and northwest side top of bridge towards bus station.

Footway reconstruction works on the northern side of Ferry Lane bridge. The northern footpath will be closed, with pedestrians diverted via a temporary crossing to the southern footpath.

21 December 2026 to 
 3 January 2027

“No works”

Christmas shutdown, with all plant and materials removed from site.

4 January 2027 to February 2027
(Phase 2)

North and northwest side top of bridge towards bus station.

Footway reconstruction works on the northern side of Ferry Lane bridge. The northern footpath will be closed, with pedestrians diverted via a temporary crossing to the southern footpath.

March 2027 to April 2027

(Phase 3)

Southeast and south side, from the Jarrow Road junction towards top of the bridge.

Footway reconstruction works on the southern side of Ferry Lane bridge. Sections of the footpath will be closed, with pedestrians diverted via a temporary crossing to the northern side. Traffic will be reduced to one lane on top of the bridge, with temporary signals in place.

May 2027 to July 2027

(Phase 4)

Southwest and south side, from the bridge towards the Bus Station

Footway works on the southern side, including junction upgrades at the bus station and new signals. Sections of footway will be closed, with pedestrians diverted via a temporary crossing. Traffic on the bridge will be reduced to one lane with temporary signals. Night resurfacing will follow, along with completion of the floating bus stop and Retail Park entrance works.

Please note that these programme phases are based on current planning and may change due to site conditions or weather. We will keep you informed of progress, and any road closures will be communicated in advance through additional letter drops and Variable Message Signs. 

What this means for you

While construction activities are underway, the following temporary traffic and access arrangements will apply at various stages of the project:

  • Pedestrian access to Tottenham Hale Station, the bus station, and all nearby homes and businesses will be maintained at all times, though routes may be slightly narrowed or temporarily diverted during the works.
  • Cycle lanes along Ferry Lane will be suspended in both directions for the duration of the works to enable construction, including the new segregated cycle tracks. These will be opened for use by cyclists at the end of the construction works. As a result, cyclists are advised to dismount and use the footway.
  • Two bus stops on Ferry Lane, eastbound near Hale Village and westbound near the park, will be suspended from around 20 August 2026 until project completion to help maintain traffic flow during the works. London Buses will coordinate alternative arrangements, which will be clearly displayed at each stop.
  • Where a footway needs to be closed for the works, we will provide temporary signalised pedestrian crossings to allow access to the other side. These will operate in line with the existing traffic signals to help minimise disruption.
  • Overnight road closures will be required on a small number of occasions to allow construction teams to safely reconfigure traffic lanes, install temporary safety barriers, and complete carriageway resurfacing. These will be clearly advertised well in advance using fixed roadside signs, Variable Message Signs, additional letter drops, and updates on our Haringey Commonplace page. All closures will take place from 8pm onwards.
  • Emergency services are aware of the works, and access will be maintained at all times.

Bus stop suspensions

To facilitate these works and maintain safe traffic flow along Ferry Lane, the two bus stops located near Hale Village (eastbound) and near the park (westbound) will be suspended September week commencing 14 September. These suspensions will remain in place for the duration of the main construction phase. London Buses will coordinate alternative arrangements, and notices will be displayed at each affected stop.

Nighttime Closures and Temporary Traffic Signals

To install temporary traffic signals and prepare for the next phase of works, a series of nighttime road closures will be required.

The closures are as follows:

  • Dates and times: Monday 9 November, Tuesday 10 November and Wednesday 11 November 2026, between 8:00pm and 5:00am each night.
  • Location: Ferry Lane between the bus station junction and Mill Mead Road.
  • Traffic impact: Vehicles will not be able to travel through this section during the closure periods. Signed diversion routes will be in place. 
  • Access: Pedestrian access to Tottenham Hale Station, nearby properties and emergency services will be maintained at all times.

Planning application designs

A plan view of the revised proposals (with pink-edged clouds showing where the designs have been improved)

View of Millmead Road Bus Stop – Artist’s impression

View looking west over Ferry Lane Bridge – Artist’s impression

View looking east over Ferry Lane Bridge and Station Entrance in daytime – Artist’s impression

View looking east over Ferry Lane Bridge and Station Entrance at nighttime – Artist’s impression 