Penstock Tunnel works progressing ahead of November completion
Improvement works on the Penstock Tunnel — a crucial link between Wood Green town centre, the Cultural Quarter, Alexandra Gate, Alexandra Palace, and Hornsey — are well underway and expected to contin
Penstock Tunnel
Improvement works on the Penstock Tunnel — a crucial link between Wood Green town centre, the Cultural Quarter, Alexandra Gate, Alexandra Palace, and Hornsey — are well underway and expected to continue until November.
As of 30 September, progress at the tunnel’s east entrance includes:
- Footway reconstruction: Substantially complete across the scheme (85%)
- Raised planter and footpath: Currently under construction
- Outstanding works: Planting, play items, and surfacing
- Timber decking:
- Western deck: Completed
- Eastern deck: Substantially complete