Broadwater Farm improvement works – September update

This update gives information on all the current improvements works happening on the estate. New home construction update Phase 1 – new homes on the Moselle site Works remain 

Broadwater Farm Estate

This update gives information on all the current improvements works happening on the estate. 

New home construction update 

  • Phase 1 – new homes on the Moselle site 

Works remain on track with expected completion date of spring 2026.   

  • Tangmere demolition 

The UKPN cabling relocation works are due to be completed by March 2026. We will include the remaining Tangmere demolition works within the Tangmere new homes  
building works. 

  • Internal strip out of Northolt 

The full internal strip-out is now complete. Demolition of the building is expected to start in early 2026. 

  • Medical Centre 

The Broadwater Farm Medical Centre is now permanently closed, with the service relocating to the Larence House Surgery, on Monday 1 September.   

The weekly repairs surgery that used to be held here has now moved to the Jazz Café in the Broadwater Farm Community Centre. This still runs every Wednesday from 11am to 1pm. 

 
Refurbishment 

  • Major works programme 

You may have started to see DCK Construction on the estate setting up their site compound with the plan start on site in October 2025.  

These major works also include the Debden undercroft and rear entrance pilot works. 

We are currently finalising the programme for the works with DCK and will be touch with residents with more information soon. 

Thank you to everyone who attended the Meet the Contractor event on Tuesday 9 September. We will be holding pop-up information sessions in communal block lobbys as the programme progresses. 

  • Pilot refurbishment – Rochford and Martlesham 

The start date for the Rochford and Martlesham pilot project has been pushed back to January 2027 while we review the procurement route for these works. The planning approval process continues with the local planning authority. 

Public space 

  • Community Centre improvements 

Phase 2 of the improvement works is on track to complete towards the end of September/early October 2025.  

Visit the improvement programme works update page to learn more about the above improvements. 