External improvements – November works schedule
Major works completed in October included liquid coating and waterproofing works, communal flooring and scaffolding removal from Debden block (along Freedom Road). Starting from Monday 2 November work
Broadwater Farm Estate
Major works completed in October included liquid coating and waterproofing works, communal flooring and scaffolding removal from Debden block (along Freedom Road).
Starting from Monday 2 November works will include:
- liquid coating and waterproofing to private balconies
- external wall painting, pigeon protection and pipework maintenance
- external timber balustrade replacement
- internal floor vinyl replacement and tiling of communal lobbies
- sandblasting and concrete repairs
Letters and notices have been issued to affected residents. If there are any changes to the works schedule DCK will inform residents directly.
Please also pay attention to all communal notices and signs which provide more information on the works happening in specific locations.
Visit the external major works programme page for the latest information and to view current parking bay suspensions on the estate.
November 2026 – planned works
- Scaffolding removal
No scaffolding removal is planned for November 2026. Please check the scaffolding removal schedule further down the page to see when the next area of scaffolding is being removed.
- Communal flooring
Lympne
Tiling works to ground-floor lobby, staircase and at the main entrance are ongoing.
Electrical lighting replacement to Lympne’s undercroft car park space continues throughout November.
Manston
Electrical lighting replacement to Manston’s undercroft car park space begins in November.
Hornchurch
Ground-floor lobby and staircase tiling works at rear emtrance are scheduled to commence on Monday 2 November.
Ground-floor lobby and staircase tiling works at the main entrance are scheduled to commence on Thursday 19 November.
Croydon
Internal communal vinyl flooring installation works are ongoing, with completion anticipated by the end of November.
- Liquid coating and waterproofing works
Liquid coating and waterproofing works to Debden block’s balconies and car park area will continue throughout November. The programme may change throughout the month depending on the weather.
- Electrical works and external balustrades replacement
Debden
The replacement of the external timber balustrades between Debden's private balconies is being undertaken. This works should be completed by the end of November.
Stapleford
Replacement of the timber balustrades along the external communal walkways and private balconies continues throughout November.
- Sandblasting works
Croydon
Sandblasting and concrete repair works continue with an estimated completion date of completion of Friday 20 November.
- External wall painting, pigeon protection and pipework maintenance works
Works are ongoing in Debden in the following areas:
- Middle section of block: 7 October to 4 November
- Gloucester Road elevation: 26 October to 20 November
External pipework maintenance is being undertaken in the following blocks throughout November:
- Stapleford
- Lympne
- Manston
Find out more
Visit the external major works programme page for the latest information.
Questions?
Contact Andrei Capinus, DCK Resident Liaison Officer, on 07463 633 467.
You can also email the Broadwater Farm Project Team at bwf@haringey.gov.uk