External wall surveys to all blocks on Broadwater Farm
Capital Property & Construction Consultants Ltd (Capital PCC) is undertaking fire safety investigation surveys to all council blocks across Haringey to help us make sure we continue to comply with
Broadwater Farm Estate

Capital Property & Construction Consultants Ltd (Capital PCC) is undertaking fire safety investigation surveys to all council blocks across Haringey to help us make sure we continue to comply with fire safety regulations.
These fire safety surveys will start on Broadwater Farm on the week commencing Monday, 27 January, with Capital PCC beginning at Kenley, Hawkinge, Stapleford, and Hornchurch blocks.
Our Residential Building Safety team has sent all residents in these blocks a letter letting them know surveys are being carried out externally to their blocks.
As the surveys progress over the coming weeks, our Residential Building Safety team will send letters to the remaining blocks on the estate to advise when to expect Capital PCC to undertake these investigations on your block.
Why are these fire safety investigation surveys needed?
Haringey Council is committed to ensuring the safety of all our residents by complying with fire safety regulations.
Significant changes have been made to these fire safety requirements, and therefore, investigations, known as Fire Risk Appraisal of External Walls (FRAEW), need to be carried out on the external walls of the block where you live to help us assess the fire resistance of all external wall construction.
What’s involved in the survey?
The survey will be undertaken externally, and access to your home will not normally be required; however, Capital PCC may need access to some private balconies and gardens to fully access the external walls. If needed, they will request permission beforehand and will be carrying an identification card showing the Capital PCC logo (shown at the top of this page).
The operatives will use a mobile elevated work platform (known as a MEWP) to undertake the survey, meaning no scaffolding will be required outside your home.
All mobile equipment will be stored securely on the estate within the site of the former Tangmere block throughout the survey works. It will take around six to eight weeks to complete the investigative surveys of all estate blocks.
Any questions?
If you have any questions, please contact our Fire Projects team at firerisk.assessmentteam@haringey.gov.uk or 07967 336217.
Stay Informed
Follow our projects to get notified of upcoming engagements and the latest project related news.