External major repairs – October works schedule
The external major works repairs and improvements works have continued to progress well across the estate this month with several key activities completed. Completed works in September included waterp
Broadwater Farm Estate
The external major works repairs and improvements works have continued to progress well across the estate this month with several key activities completed.
Completed works in September included waterproofing works, pigeon protection measures, sandblasting, and improvements to communal areas across Debden, Hornchurch and Manston.
Please visit the external major works programme page to see the photo gallery of all the latest works.
Starting from Thursday 1 October works will include:
- scaffolding removal from Freedom Road (along Debden block only)
- liquid coating and waterproofing works
- communal flooring, undercroft lighting and external balustrades replacement
- sandblasting works
- external wall painting, pigeon protection and pipework maintenance works
Letters and notices have now been issued to affected residents. If there are any changes to the works schedule DCK will inform residents directly.
Please also pay attention to all communal notices and signs which provide more information on the works happening in specific locations.
October works schedule
- Scaffolding removal
The scaffolding will start to be removed on Freedom Road, along Debden block only (outside flats 21 to 22 and 25 to 34): from Thursday 1 October.
You can see the planned scaffolding removal for other blocks on the estate on the external major works programme page.
Liquid coating and waterproofing works
Liquid coating and waterproofing works to Debden block’s balconies and car park area will continue throughout October. The programme may change throughout the month depending on the weather.
Communal flooring, undercroft lighting and external balustrades replacement
- Lympne
The floor tiling is being replaced in the following locations:
- ground-floor lobby at the main entrance: starting 12 October
- ground-floor staircase at the main entrance: starting 26 October
- Electrical lighting replacement to Lympne’s undercroft car park space: starting 1 October
- Hawkinge
- new vinyl internal flooring works in the communal corridors, outside flats 1 to 12 and 27 to 36: starting 5 October
- Stapleford
- replacement of the timber balustrades to private balconies and along communal external walkways: starting 1 October
Sandblasting works
- Croydon
Sandblasting and concrete repair works will be undertaken at Croydon in the following locations:
- along Freedom Road, outside flats 12 to 21 and 42 to 51: from 28 September to 9 October
- the main entrance and middle section in the undercroft car park: from 12 to 23 October
- along Freedom Road, outside flats 1 to 7, 24 to 37 and 54 to 74: from 26 October to 20 November
Parking bay suspensions will be in place throughout the works. Signs and barriers will be displayed to let residents know suspension locations.
External wall painting, pigeon protection and pipework maintenance works
- Debden
External wall painting, pigeon protection works and drainpipe maintenance is continuing in the following areas:
- the middle section of Debden undercroft car park space: from 5 to 23 October
- undercroft car park space located on the Gloucester Road side of the block: from 26 October to 11 November
Parking bay suspensions will be in place throughout the works. Signs and barriers will be in place to let residents know suspension locations.
Find out more
Visit the external major works programme page for the latest information.
Questions?
Contact Andrei Capinus, DCK Resident Liaison Officer, on 07463 633 467.