Improvement works programme – June 2026 update

This update gives information on all the current improvements works happening on the estate. New homes Phase 1 new homes - Freshwater Court Freshwater Court is now complete with residen

Broadwater Farm Estate

This update gives information on all the current improvements works happening on the estate. 

  • New homes 

Phase 1 new homes - Freshwater Court 

Freshwater Court is now complete with residents moving into their homes from early June. 

Former Tangmere site

New home construction is due to start this summer.  

The drainage work on Gloucester Road - causing the road closure and bus diversion - is now complete. Cadent Gas Ltd is currently carrying out necessary gas pipe rerouting works (needed for the new homes construction) on Willan Road.  

Neighbouring residents are being contacted by independent surveyors re boundary wall matters. More news on construction start date and Meet the Contractor event coming soon. 

Northolt and Stapleford North 

Willan Road is currently closed to allow for the re-routing of pipework for the upcoming demolition of the buildings. We expect the road to reopen on Monday 22 June.  

Demolition works will start once the pipework rerouting works are complete. 

We are planning a joint Meet the Contractor event with the New Home contractor – Formation – and demolition contractors – Erith – over the summer. More news on this to follow. 

  • Refurbishment 

Major works programme 

External repairs and communal flooring replacements continue across the estate: 

  • Structural works are now mostly complete, with high lever concrete repairs and removal of existing coatings almost finished.
  • Low level works to car parkundercroftareas and the first floors has begun on the estate but is notcurrently underwayall blocks.
  • The next phase of the programme will focus on finishing works to improve appearance,safetyand overall building quality.

Pilot refurbishment – Rochford and Martlesham
Planning consent was granted in January 2026. We are now working with consultants and contractors to meet Building Safety Regulator requirements. The project remains on track to start in January. 

  • Public space 

Debden pilot undercroft project
Works have begun alongside the major works programme. We are commissioning artists to support co-design workshops with residents. More on this to come.

Learn more about the full programme of improvements 

Visit the improvement programme works update page to learn more about the above improvements. 

View the project timeline for an overview of each stage of the programme. 