Hello,We’re continuing to make strong progress at the Civic Centre site and are pleased to share the latest updates from September.Externally, scaffolding works are now complete around the main buildi

Haringey Civic Centre Redevelopment

Hello,

We’re continuing to make strong progress at the Civic Centre site and are pleased to share the latest updates from September.

Externally, scaffolding works are now complete around the main building, including the temporary roof, with additional scaffolding progressing on the Committee Rooms wing. The new substation near Bounds Green Road is taking shape, with its shell and roof now fully built. Service ducts have been installed in the courtyard, paving the way for new drainage connections.

Inside the Civic Centre, demolition works have continued across the basement and upper floors. The link between the Annex and the main building is progressing well, with columns and the ground floor slab now poured.

In the Annex, the core stairwell and lift shaft structure are now complete on the ground floor, and new stairwells and lift shafts have been installed. The first-floor concrete slab has been poured. A mock-up of the Annex’s front cladding panels has also been completed, offering a preview of the final finish.

Coming up next: we’ll be installing the first-floor columns in the Annex with reinforced steel, preparing for roof replacement on the existing building, carrying out repairs to the existing brick and stonework, and continuing internal demolition and drainage works.

As always, we’re committed to being good neighbours during construction. If you have any questions or would like to learn more about careers in construction, please reach out to our build partners at civicconstruction@sisk.co.uk.

Best regards,
The Civic Centre Team