Penstock Tunnel works progressing ahead of November completion

Improvement works on the Penstock Tunnel — a crucial link between Wood Green town centre, the Cultural Quarter, Alexandra Gate, Alexandra Palace, and Hornsey — are well underway and expected to contin

Penstock Tunnel

Improvement works on the Penstock Tunnel — a crucial link between Wood Green town centre, the Cultural Quarter, Alexandra Gate, Alexandra Palace, and Hornsey — are well underway and expected to continue until November.

As of 30 September, progress at the tunnel’s east entrance includes:

  • Footway reconstruction: Substantially complete across the scheme (85%)
  • Raised planter and footpath: Currently under construction
    • Outstanding works: Planting, play items, and surfacing
  • Timber decking:
    • Western deck: Completed
    • Eastern deck: Substantially complete