Project

Improvement works programme – December 2025 update

This update gives information on all the current improvements works happening on the estate. New homes construction updates Phase 1 – new homes on the Moselle site Works remain on track with expected

Broadwater Farm Estate

This update gives information on all the current improvements works happening on the estate. 

New homes construction updates 

  • Phase 1 – new homes on the Moselle site 

Works remain on track with expected completion in March 2026.  

Housing needs assessments of former tenants of Tangmere, Northolt and Stapleford North blocks wanting to return (Right to Return residents) is now complete.  

All Broadwater Farm residents were sent information on how to express their interest in a new home on the estate in December 2025. Learn more on the Broadwater Farm new homes allocation page. 

On site works finished for the festive break on Friday 19 December. Works will recommence on Monday 5 January 2026. 

  • Tangmere demolition 

UKPN is recommencing the cabling relocation work from Monday 5 January 2026. 

Willan Road pedestrian footpath will be closed from Monday 8 to Sunday 14 January. The road will remain open to vehicles.  

There will be an electrical power outage on Willan Road on Friday 9 January. 
UKPN will contact any impacted residents before works begin.  

Read the latest update to learn more about these works and how they may impact you. 

Formation Design and Build has been awarded the new homes contract and will be completing the demolition from March 2026 ready for starting construction works. 

  • Northolt and Stapleford North demolition 

Purdy Contracts will be rerouting the buildings water services and pipe work in early 2026 in preparation for demolition from March. 

These are isolated works which shouldn’t impact residents until late January when Willan Road will have to close for one week while pipework is reconnected to Stapleford. We will update residents in early to mid-January once dates for this road closure have been confirmed. 

 Refurbishment updates 

  • Major works programme 

Scaffolding is now installed at Debden, Hornchurch and Stapleford. 

Sandblasting works to residential balconies, and the undercroft car parking spaces has now started in Debden.  

Parking suspensions are now in place on Freedom Road and Gloucester Road to allow for more scaffolding to be installed. Notices are in place. Please do not park in the suspended bays – cars will be removed and residents charged for their return.  

A new door entry system is being installed to Hawkinge in January 2026 – residents have been contacted. 

On site works will finish for the festive break on Tuesday 23 December. Works will recommence on Monday 5 January 2026.  

All scaffolding has been secured and should not be accessed during this time. If you notice anyone on the scaffolding during this shutdown period (Wednesday 24 December 2025 to Monday 5 January 2026) and feel concerned in any way, please contact the police. 

  • Pilot refurbishment – Rochford and Martlesham 

The start date for the Rochford and Martlesham pilot project has been pushed back to 2027 while we review the procurement route for these works. The planning approval process continues with the local planning authority.  

Public space improvement updates 

  • Community Centre improvements 

The final upgrade to the Community Centre is the replacement of the floor tiles in the main entrance and reception. This is now due to be completed in January 2026. 

  • Debden pilot undercroft project 

Works have begun as part of the major works programme. The bulky waste bin collection area has now been moved to make way for the new walkway through to Lordship Recreation Ground. Please view the updated bulky waste map to see the new Debden collection point. 

On site works will finish for the festive break on Tuesday 23 December. Works will recommence on Monday 5 January 2026. 

Learn more about the full programme of improvements 

Visit the improvement programme works update page to learn more about the above improvements. 

View the project timeline for an overview of each stage of the programme. 

You can also visit the Broadwater Farm page on Haringey's website to learn more about: 

Stay Informed

Follow our projects to get notified of upcoming engagements and the latest project related news.