Bypass Signalization Upgrades
Project Overview: Signalization Upgrades along US Hwy 70S/SR-1, from N. Chancery St. to Mall Drive (5 intersections excluding Mullican St.);
Intersections
- N. Chancery St. and SR-1
- Smithville Hwy. and SR-1
- N. Chancery St. at Wal-Mart Entrance
- N. Spring St. and SR-1
- Red Rd. and SR-1
Components
- New Radar Detection to Replace Underground Loops
- New Signal Heads
- New Control Cabinets
Funding
The Bypass Signalization Upgrades Project is funded through a Traffic Signalization Grant that totals $898,072.20 with the City of McMinnville having a match totaling $179,614.60
Stay Informed
Get notified on upcoming engagements and the latest project related news.
Project Schedule
Begin NEPA Phase
January 2024
Select Consultant
January 2024
Submit Environmental Documents to TDOT for Review
January 2024