Brinklow Roundabout Improvements - April 2025
Following up on our recent vegetation clearance and electrical cable testing works carried out in February, our main contractor, Ringway, will be carrying out essential investigation works in the Brin
Highways Major Projects
Following up on our recent vegetation clearance and electrical cable testing works carried out in February, our main contractor, Ringway, will be carrying out essential investigation works in the Brinklow Roundabout. The works comprise of several trial holes to confirm the location of existing utility apparatus prior to commencing the main construction works. These are essential to ensure that there are no services at the proposed location of foundations for the new traffic signal poles. This work could not be carried out at the time of the vegetation clearance due to health and safety concerns, and there would have been too much conflict with construction traffic and work personnel. Attached the trial holes plan.
The works are planned to commence on Monday, the 7th April, and these will be outside peak hours and during the Easter School Holidays, to minimise disruptions in the area. Please note that the temporary traffic management (TM) will be installed and removed every day, so during the peak hours there will be no restrictions.
These works will be carried out under lane closures from 9:30 to 16:30. Ringway will need to allow approximately 1 hr to set up and take down the temporary traffic management; the likely working window will be 10:30–15:30, subject to on-site assessment of traffic flows by our contractor/engineers.
Attached is an indicative lane closure plan similar to the one introduced in Feb, but on Thursday 10th April the TM will be adjusted with an additional left-turn lane closures on Winchester Close from Kingston Centre to Tongwell Street and Etheridge Avenue from the Brinklow Industrial Estate to the A421 Standing Way for safety reasons and proximity to where some trial holes will be carried out.
The duration of these advance works will be subject to the completion of the required tasks and weather dependency; therefore, 5 days of this week commencing on 7th April have been reserved for these works.
The main construction works have been reprogrammed to start in June 2025, due to delays in delivering traffic signal equipment and to include all necessary maintenance works in the area to be carried out at the same time.
With regards to the main construction works, further updates will be provided when the programme is agreed.
Further details regarding road restrictions and diversion routes can be found on our website https://www.milton-keynes.gov.uk/highways/major-projects
Highways Major Projects Team