Brinklow Roundabout Improvements - July 2025
The main phase of the roundabout improvement works began on 15 June. Since then, we have:- Installed most of the ducting for the traffic signals, streetlights and signage. The special socket for the s
Highways Major Projects
The main phase of the roundabout improvement works began on 15 June. Since then, we have:
- Installed most of the ducting for the traffic signals, streetlights and signage. The special socket for the signal posts will be in place by the end of July.
- Cable inspection chambers are being constructed and will be completed by early August.
- The damaged block paving in the inner roundabout area has been removed. This section will be resurfaced as part of the final phase of the project.
- Cleaned, repaired and repainted the parapets and railings.
Next steps
- In the next four weeks we will be:
- Adding or improving new streetlights
- Installing signage
- Install foundations for traffic signal masts
- Improve the bus shelters
Further phase of works will include:
- Resurfacing
- Road markings
- Road studs
Further details regarding road restrictions and diversion routes can be found on our website https://www.milton-keynes.gov.uk/highways/major-projects