The State & Main Street Reconstruction Project, also called the East State Street Reconstruction project, is currently underway! Infrastructure upgrades scheduled for Downtown Montpelier include new water/sewer/storm infrastructure, new sidewalks, and necessary road reconstruction. Due to the large scope, this project has been constructed and bid in two contracts.

Contract 1 - "State and Main St Stormwater Improvements" - Construction beginning March 2025, project area from Rialto Bridge to Main/State intersection. Hebert Excavation has been contracted to complete the work.

Contract 2 - "East State St Reconstruction Phase 2" - Construction anticipated 2026, project area from Main/East State St intersection to College St.

ANSWERS TO FREQUENTLY ASKED QUESTIONS FOUND BELOW IN THE "SUPPORTING DOCUMENTS" SECTION.

Vortech Separator and Jellyfish filter
Justin LaPerle
Justin LaPerle
Lead Construction Engineer, Montpelier Department of Public Works

Project Timeline

Contract 1: Bid Award & Construction Preparation
November 2024 - February 2025
Contract 2: Final Design
December 2024 - March 2025
Contract 1: Construction Begins
March 2025 - June 2025