Much needed rain finally came. Unfortunately, that did delay construction a little. The last little bit of concrete work needs to be completed before the final layer of asphalt can be placed. As of today, concrete is scheduled for Friday 6/20 and asphalt on Monday 6/23. (Seaway to Division)
We are attempting to open Division before proceeding too far west. Once Division is open; say middle of next week; we will begin work stretching all the way to Lakeshore Drive. First, we will remove manhole covers and then mill the pavement off. That could occur as soon as next week! Then, we will move west with underground work, including water service replacement.
Again, please plan accordingly.