Construction Update

Work is progressing!

Lakeshore Drive Road Rehabilitation 2026

Most of the water services are replaced. The underground work is wrapping up. Concrete was placed this week. All is looking good.
Things to be aware of:
-The mill should be here either Monday or Tuesday. This is a large and noisy piece of equipment. Stay away and try to stay of the road and out of the way. It also means lots of truck will be coming and going. Please be careful.
-The first layer of pavement is tentatively scheduled for May 7 or 8. The new road CANNOT be drove on for at least an hour. Please plan accordingly. Also note, it's only the base layer.

We are on track to have this phase completed by the end of May. Working together makes a smoother project.