Grant Extension
On October 28, city staff were notified that the $2.8 million MEDC grant extension had been approved, giving the project until September 30, 2027, to complete the work. A grant amendment has since been signed.
Before the extension was approved, the city and its engineering firm, Progressive Companies, were working quickly to spend the grant funds before the end of the year. This included putting the project out to bid.
With the extension in place, the city stopped the bidding process and returned the unopened bids. The project will now follow the standard construction bidding and approval process, as outlined in the motion approved by the City Commission on September 22, 2026.
Construction Timeline & Purchasing
Construction is now expected to begin in spring 2027. Progressive Companies is updating the project timeline and finalizing the planning and design work to prepare for construction.
To help keep the project on schedule, the city may purchase some materials ahead of construction, including benches, waste receptacles, and lighting components. These items can take months to arrive, so ordering them early may help prevent delays.
Any advance purchases will follow the city's normal purchasing policy and may appear on future City Commission agendas.
USS LST 393 Relocation
Mart Dock continues working on plans to relocate the USS LST 393. Designs and surveys are underway to make sure the work does not interfere with the nearby sewer system.
Staff is also working with Mart Dock on a property easement to connect the bike path to the new Third Street property.
The city and Mart Dock are also finalizing a sub-grant agreement outlining how Mart Dock will use state grant funds for the LST relocation. The agreement will allow Mart Dock to manage its own purchasing process and request reimbursement from the $2.8 million grant allocation. The sub-agreement must be approved by the Michigan Economic Development Corporation (MEDC).
Property Update
The county has assigned a new address to the recently acquired 3.12-acre property. The property is now located at 780 Terrace Point Drive.
Public Engagement
The October 20 public engagement event was successful, with close to 100 community members and stakeholders attending. Participants shared ideas and feedback about how the waterfront park could be designed to best serve the public. An online survey was availble for those who were not able to attend. The survey closed on November 4.
Progressive Companies is expected to send the city a summary of the feedback in late November. It will be shared on the project page.
Next Steps
Progressive Companies is expected to provide one more update to the City Commission and prepare the plans and documents needed to put the project out to bid in April 2027.