Accepted 10-year Plan

On November 18, 2026, the Nantucket Select Board approved the Nantucket Sediment Transport Study and Dredge Plan. This was the final step in the plans development, after the Harbor and Shellfish Advisory Board and the Coastal Resilience Advisory Committee both approved the Plan on November 3, 2026.

Project Purpose

The Nantucket Harbors Sediment Transport Study and Dredge Plan supports the Town’s understanding of sediment transport within Nantucket, Madaket and Polpis Harbors through a data-driven modeling approach informed by the community’s coastal resilience goals. The outputs of this effort created a guide to decision-making and maximize sediment resources on Nantucket and improve navigation in the harbors for the benefit of the public.

Project Overview

Sedimentation in the harbors is an obstacle to navigation and many activities on Nantucket, from recreational sailing to essential travel to and from Cape Cod. Additionally, to effectively implement many of the erosion management recommendations made by the Coastal Resilience Plan (CRP) in 2021 and the Hazard Mitigation Plan (HMP) in 2019, additional data collection and analysis was necessary to understand sediment movement. A sediment transport study was a priority recommendation of the CRP to understand sand and sandbar movements. Delivery of this plan fulfilled CRP recommendation #1-8 to develop a Sediment Transport Study. To fill the need identified in the CRP and address maritime navigational needs, the Nantucket Harbors Sediment Transport and Dredge Plan kicked-off in April 2023, with an emphasis on potential beneficial reuse of recovered materials. This initial effort prioritizes understanding sediment transport in Nantucket Harbor, Madaket Harbor and Polpis Harbor as these areas are critical to navigation.

Data collected throughout this process and outputs of the sediment transport model helped guide resilient decision-making by identifying sediment resources and prioritizing erosion management locations; identify opportunities for the development of an island sand bank; collect data to better understand and protect sensitive habitats; and inform other completed and ongoing sediment management efforts.

Project Timeline

The Nantucket Harbors Sediment Transport and Dredge Plan began in April 2023. Field data collection in May 2023 included bathymetric survey, sediment coring and water level monitoring and informed the sediment transport model. From spring 2023 through spring 2024, the sediment transport model will be developed using the best available data and state-of-the-art modeling approaches. Stakeholder feedback was initiated in Fall 2024. Using the outputs of this model and stakeholder feedback, the project team will identify and prioritize opportunities for dredging and beach nourishment and assist the Town in securing required permits for priority projects. Permitting for two key areas – Entrance to Polpis Harbor and Hither Creek in Madaket began in early 2025. Several permits were received beginning in late 2026 and throughout 2026. Drafting of the final plan began in early 2026 and was completed when the plan was approved in November 2026 by (i) Harbor and Shellfish Advisory Board, (ii) Coastal Resilience Advisory Committee and (9iii) Select Board.

Next steps include undertaking a required Environmental Impact Report and seeking bids for dredging. Dredging may commence from fall 2027, and be undertaken over the next 10 years.

Project Team

The Town of Nantucket is leading the Nantucket Harbors Sediment Transport and Dredge Plan. Working closely with the consultant team, Town staff will direct contact with local resources as well as state and federal agencies. The Nantucket Harbors Sediment Transport and Dredge Plan required survey and field work, state-of-the-art sediment modeling, dredge and erosion management planning, and sensitive habitats protection to make the project successful. To support this work, an interdisciplinary team of consultants led by Dutch engineering firm Arcadis and including Baird & Associates, Tighe & Bond and Alyssa Novak, PhD. worked directly with Town staff.

Nantucket Harbor

Stay Informed

Get notified on upcoming engagements and the latest project related news.

Sustainability Programs Manager Vincent Murphy
Sustainability Programs Manager Vincent Murphy
Town of Nantucket Natural Resources Department

Project Phases

Sediment Transport Study

Spring 2023 – Spring 2024

Dredging Research & Engineering

Summer 2024 - Spring 2025

Permitting

2025 - 2026

Final Report

November 2027

Dreding

Fall 2027 - 2036