Sea Street Pump Station Force Main No.3 Project Update
Sea Street Pump Station Force Main No. 3 Project Nearing Completion
The fourth and final year of construction for the Sea Street Pump Station Force Main No.3 project began on September 2, 2025. During the month of December, Robert B. Our Company (RBO) advanced final restoration work along the project route in coordination with their subcontractor, MTK. The following activities were completed during the month of December:
• Completion of driveway apron restoration work on South Shore Road.
• Loaming of disturbed areas on South Shore Road.
• Installation of outstanding sewer force main manhole appurtenances along the project route.
• Decommissioning and removal of sewer force main bypass piping at the SSWWTF.
• Commissioning of the new sewer force main.
Currently, the Sea Street Pump Station Force Main No.3 project is substantially complete. RBO will return in the spring to complete outstanding punch list items such as seeding of loamed areas, installation of permanent thermoplastic pavement markings, miscellaneous restoration work, and final cleanup.