Tom Nevers Park Debris Removal and Erosion Control/Dune Restoration

Tom Nevers Debris Removal

2026 Annual Town Meeting & Election

Article 16, Appropriation: Tom Nevers Debris Removal and Erosion Control/Dune Restoration, passed at both Town Meeting and the Annual Town Election.

The article authorizes a debt exclusion of $8,000,000 for the project. At Town Meeting, the required two-thirds vote was achieved, with 304 in favor and 116 opposed. At the election, Question 5 passed with 1,885 yes votes and 1,008 no votes.

The Town is now working on next steps; please visit this page soon for more details and updates.

Phase Two Project Summary

This project includes the removal of subsurface (buried) debris in the main area of the park between the bunker and bluff, east of the phase one project site. Removal of this buried debris before erosion exposes it on the bluff face or causing it to land on the beach is much more efficient and cost effective.

Before and after phase 1 photos

Phase One Project Summary

This project includes the removal of subsurface (buried) debris on the west side of the park, structures and other debris on the beach, removal of debris protruding from the bluff face, and construction of a beach access ramp for future debris removal by DPW.

Project Area

  • West of the Hockey Rink and Dirt Track
  • Beach area and bluff face

Phased Approach

  • Phase One: Focuses on the removal of subsurface debris within the ramp footprint, debris on the beach and high tide line, and debris protruding from the bluff face.
  • Phase Two (future): Continues the removal of subsurface debris inland from the bluff face to prevent it from becoming beach debris in the future (FY27 Capital Request).

Phase One

Beach Access Ramp

  • The ramp will remain at the end of Phase One to allow DPW beach access for future debris removal.
  • The ramp will remain in place until the bluff face and the southern limit of the Phase Two project area meet, at which point it will be removed and the ramp area will be revegetated.
  • The ramp will not serve as a public vehicle access point.
  • Sacrificial sand will be installed at the southern (beach) end of the access ramp to prevent wave action from eroding the surface and sides of the ramp.

Challenges

  • Permitting: timelines and deadlines for contracts and construction activities
  • Winter coastal construction
  • Potential unexploded ordinances

Other Related Projects

  • Tom Nevers Hockey Rink Reconstruction (FY27 Capital Request)
    • Same construction method (post-tensioned concrete) as new Jetties Tennis Courts
    • Existing base will be pulverized in place and graded to serve as a new base layer for the concrete slab
    • New layout will be cross-lined for basketball, tennis, pickleball, and roller hockey
    • New vinyl coated chain link fence above four-foot-high boards
    • Basketball hoops installed to match existing layout
    • All other nets (tennis, pickle, roller hockey) will be portable to allow maximum flexibility for a variety of uses and configurations
    • New multi-sport court will add to Tom Nevers Park, which will soon be the end point of the new Tom Nevers Bike Path
  • Playground was updated in Spring 2025
  • Improved irrigation, fencing, and infields softball and baseball fields
  • Tom Nevers Bike Path (construction anticipated to start fall 2026)

Project Updates

To Nevers aerial image

Stay Informed

Get notified on upcoming engagements and the latest project related news.

PROJECT TIMELINE

$2M appropriated (2024 ATM, Article 15)

May 2024 Annual Town Meeting

Weston & Sampson engineers begin design and permitting

September 2024

A set of winter storms claim 40 feet of bluff face

December 2024