Utilities Building Construction Project

The City of North Port has started construction on a Utilities administration building and field office, marking a significant step towards reuniting staff and enhancing operational efficiency.

The site is situated off Pan American Boulevard between the Willow Creek development and the future Waters at North Port development.

The new building will replace the former Utilities facility on Price Boulevard, which was rendered uninhabitable by Hurricane Ian in September 2022. Since then, field staff have been operating from modular offices at the Price Boulevard site, while administrative staff are scattered across various locations, including plants and other City facilities. The project is designed by Stantec and is being constructed by Seagate Construction.

Construction is expected to be completed by the fall of 2026, at which time all Utilities staff will be reunited under one roof, facilitating better collaboration and streamlined operations.

Important Links

For more information about the Utilities Department, see the video below.

Utilities Building Groundbreaking, Construction, Projects, North Port

Stay Informed

Get notified on upcoming engagements and the latest project related news.

"The construction of our new utilities administration building represents a new chapter for our Utilities department. After the challenges posed by Hurricane Ian, we're excited to provide our customers and staff with a modern, resilient facility that will enhance our ability to serve our community."
Tricia Wisner
Tricia Wisner
Director of Utilities

Project Timeline

Budget Signed off by Commission

Winter 2024

RFP For Developer/Contractor Sent Out

Spring 2025

Groundbreaking

Spring 2025

Project Update 05-22-2026
Work accomplished:

  • 1st lift of asphalt work completed for entire UAB site
  • HVAC work continues in Sector A (Admin) North & South Bldgs
  • Sector C (Warehouse) roof dried in w/peel & stick
  • Drop ceiling metal frame work continues in Sector A (Admin)
  • Insulation work continues in Sector B (Operations) Bldg
  • Exterior lighting installed at Sector B (Operations) & Sector C (Warehouse) Bldgs
  • Concrete Curbing installed at employee parking area
  • Installed 324 LF of 8” gravity sewer main from King Manhole (#9) to Manhole #8
  • Installed 46 LF of 8” gravity sewer main from Manhole #8 to Existing UAB Manhole #5
  • Installed Approx. 820 LF of 6” DR 18 Force Main Pipe, (2) 6” 45 deg bends along Childrens Way toward new Lift Station site.
  • Sewer Low Pressure Air Test conducted from Lift Station to Existing UAB MH #5
    • Test Result-PASSED

Project Update 06-04-2026
Work accomplished:

  • Paving is underway
  • Fire damage to the outside of the warehouse has been repaired
  • Drop Ceiling and drywall being installed
  • Outside paneling being installed

Updated Works Pictures