The City of Oak Ridge is turning 4.6 miles of abandoned CSX railroad within the city into a greenway for pedestrians and bicycles as part of an ongoing project named Rails to Trails. The greenway will extend from Elza Gate at the Oak Ridge Turnpike, along Fairbanks Road, Warehouse Road, Lafayette Road, and across S. Illinois Avenue to the Y-12 National Security Complex.

The Rails to Trails project began in July 2017 with Oak Ridge City Council approving a funding agreement with the Tennessee Department of Transportation (TDOT), stating in which TDOT would cover 80% of the estimated $1.53 million project cost.

Back in November 2021, a public meeting was held to present the proposed trail design and gather community feedback. The next phase of the project is now set to begin with TDOT being issued a notice to proceed with right-of-way acquisition in September 2024, marking a major milestone as the project moves closer to construction.

View a photo album of the trail lines set to become greenways

Overview of the proposed Rails to Trails intersections

Opportunities to Engage

Stay Informed

Get notified on upcoming engagements and the latest project related news.

"This greenway is going to connect a lot of people across the City, serving as an alternative transportation and a recreational amenity."
Jon Hetrick
Jon Hetrick
Director of Recreation and Parks

Project Updates

Important Dates

3
Jul 2017

Project Begins

The Rails to Trails project was initiated in the City of Oak Ridge to turn 4.6 miles of abandoned CSX railroad tracks into a walkway for pedestrians.

11
Jul 2017

Council Approves Agreement With TDOT

City Council approves an agreement with Tennessee Department of Transportation (TDOT) for Rails to Trails project in the estimated amount of $1,530,000 with TDOT reimbursing the city for 80% estimated at $1,224,000 and the city responsible for 20% local match estimated at $306,000.

20
Jul 2017

City gets the Notice to Proceed to consult an engineering firm

City of Oak Ridge gets the notice to proceed from Tennessee Department of Transportation to consult with an engineering firm to do all phases of preliminary work.

25
Jul 2017

Project Agreement

City of Oak Ridge and Tennessee Department of Transportation come up with an agreement on the phases and due date of Rails to Trails.

13
Sep 2017

City of Oak Ridge requests engineering firms qualifications and Letters of Interest.

City of Oak Ridge sneds out a notice to consultant engineers for a request of qualifications and letters of interest.

7
Dec 2017

City of Oak Ridge Interviews engineering firms

City of Oak Ridge makes a list of top engineering firms and invite them to interview for Rails to Trails project.

8
Jan 2018

City of Oak Ridge decides to go with A. Morton Thomas & Associates, Inc. for Rails to Trails project

City of Oak Ridge ranks the engineering firms that they interviewed and ultimatley choose A. Morton Thomas & Associates, Inc. to be the engineering firm on the project Rails to Trails.

18
Jan 2018

City of Oak Ridge makes an estimate on Rails to Trails project.

City of Oak Ridge drafts an Independet cost estimate and scope of work for, NEPA, Design, ROW and CEI. the total estimate came out to be around $1,381,200.

14
Jun 2019

AMT outlines project plan and required forms for the agreement

A. Morton Thomas & Associates, Inc sends the Cityof Oak Ridge an outline plan of the project and required forms for the project for their agrrement.

21
Apr 2020

City receives notice to proceed with preliminary engineering for final design phase.

City of Oak Ridge receives notice to proceed with preliminary engineering for finsl design phase.

10
Nov 2021

Drop in Public Meeting

The City held a drop in public meeting in the Oak Ridge Civic Center Gym, to present the trail design and next steps for the project, and to seek input from residents.

1
Sep 2024

TDOT given notice to proceed

TDOT was given the notice to proceed and right-of-way acquisition (ROW)