2017 Project 12: New Path Connection - Peachtree Parkway N: Flat Creek Road to Interlochen
Project/Goal Description: New path along North Peachtree Pkwy to provide connectivity from Flat Creek Rd. to Interlochen Dr.
Final Update: This project was completed in 2021. Public Works designed, constructed, and negotiated the property acquisition for this path connection.
SPLOST Actuals Total: $80,012
SPLOST Funds Over Budget: $(37,300)
The original budget estimates were developed without the benefit of final engineering drawings; therefore, changes had to be made for safety and constructability while restraining overall costs. For example, the amount of right-of-way needed was larger than originally anticipated.