2017 Project 15: New Path Connection – Crosstown Road (south side)

Project/Goal Description: New path at Crosstown between Wendy’s and Flash Foods.

Final Update: Public Works constructed this short path connection between Wendy’s and the gas station.

SPLOST Actuals Total: $526

SPLOST Funds Under Budget: $6,554

road

Stay Informed

Get notified on upcoming engagements and the latest project related news.

Project Phases

Category
Multi-Use Path System
Location
Crosstown Rd
Original Project Budget
$7,080