Status: In progress
Location: Huddleston Rd
Proposed Project Year: 2023
Original Project Budget: $206,000

Project Description:

New path along Huddleston Rd from Paschall Rd tunnel access at HWY 74.

June 2024 Progress Update:

As of 10/5/23 Agreement with WASA approved.

December 2023 Progress Update:

City Staff is currently preparing to send out a request for proposal for design services.

SPLOST Funds Remaining: $206,000

Stay Informed

Get notified on upcoming engagements and the latest project related news.

David Borkowski
David Borkowski
City Engineer

Project Phases

Concept
Completed
Design
Completed
Bid
Completed