Peachtree City, GA
Paths

2023 Project 30 - Grade Separated Crossing to Connect Booth Middle and McIntosh High

Project Status: In Progress
Location: Not Determined
Estimated Cost: $4,000,000

Project Description

Currently, there is no direct path access across this area of Hwy 54. If a person wanted to go from Booth Middle School to McIntosh High School via golf cart, they would have to go 3.2 miles to tunnel T-21 near McDonald's to cross Hwy 54.

This project is proposed to include a feasibility study of potential locations and to recommend whether the crossing be a bridge or tunnel. It would also include the design and construction of the project as well as any land and/or easement acquisitions.

Update 2/6/25

Feasibility study presented to 2/6/25 Council Meeting.


Proposed Photo

2023 Project 30 - Grade Separated Crossing to Connect Booth Middle and McIntosh High

Stay Informed

Get notified on upcoming engagements and the latest project related news.

David Borkowski
David Borkowski
City Engineer

Project Phases

Concept
Completed
Design
Completed
Bid
In Progress