Project
Start of Construction Update
Chase Excavating intends to mobilize to the site starting July 6, 2026. Construction will be focused on the Fish Pier property from July through the end of September. Work is scheduled to extend into Commercial Street beginning in early October.
Please note that traffic impacts on Commercial Street are expected to be minimal for the first few months of the project until the work moves into the roadway in October.
Commercial Street and Portland Fish Pier Storm Drain Outfall Project
Project Look Ahead
Mobilization
July 6 - July 11, 2026
Support of Excavation Installation
July 11 - July 31, 2026
Fish Pier Drainage Phase A
July 31, 2026 - September 3, 2026
Outfall, Tideflex Vaults and Valves
Stay Informed