Start of Construction Update
Project

Start of Construction Update

Chase Excavating intends to mobilize to the site starting July 6, 2026. Construction will be focused on the Fish Pier property from July through the end of September. Work is scheduled to extend into Commercial Street beginning in early October.


Please note that traffic impacts on Commercial Street are expected to be minimal for the first few months of the project until the work moves into the roadway in October.

Commercial Street and Portland Fish Pier Storm Drain Outfall Project

Project Look Ahead

Mobilization

July 6 - July 11, 2026

Support of Excavation Installation

July 11 - July 31, 2026

Fish Pier Drainage Phase A

July 31, 2026 - September 3, 2026
Outfall, Tideflex Vaults and Valves