Contract Award and Preliminary Schedule
Contract Award and Preliminary Schedule Information
Commercial Street and Portland Fish Pier Storm Drain Outfall Project
The City of Portland has succesfully bid this project and awarded a construction contract to Chase Excavating for a total contract price of 6.26 Million Dollars. A project kickoff meeting was held at DPW offices on 1/21/2026 with the Contractor and City project team.
The contractor has provided the following preliminary information regarding the project schedule:
**Mobilization — **July 2026
Construct Fish Pier Drainage (Phase 1) — July 2026 to September 2026
Pave & Turnover Fish Pier Parking Lot — October 2026
Commercial Street Drainage (Phase 2) — October 2026 to May 2027
Pave Commercial Street & Surface Fish Pier — May 2027
Mill & Overlay Commercial Street Trenches — May 2028