Construction Update #4
Project

Construction Update #4

Spring exterior work is ramping up!

Rising Eddy Community Pool Project

Thank you for your continued interest in Rising Eddy Community Pool Project construction formally known as Kiwanis Pool! Work has continued inside the building throughout the winter and outside work is starting to pick up.

WHAT TO EXPECT THIS SPRING:
● Continued tenting to for installation of pool tiles.
● Continued interior work on both buildings
● Form work and pouring of the concrete for the splash pad.
● Drainage line work will take place in St. James Street and provide an upgraded drain pipe to Douglass Street.
● Soil stockpiles will remain covered by plastic but work on the field is anticipated to begin this spring.


LIBBYTOWN COMMUNITY GARDEN:
● The water line is fully installed and when the seasonal water is turned on the spigots should be fully operational.

OTHER ITEMS:
Please use SeeClickFix to document non-emergency issues relating to park use, and 911 for emergency situations relating to public safety.

Sneak peak of the tile being installed.
Pool perimeter fence being installed.