The In-River Park contractor completed installation of flowable concrete on an in-stream structure this week, marking significant progress on the project's water-based construction. Crews scheduled the concrete work early to minimize disruption to Greenway users and allow maximum curing time during daylight hours. With this work complete, the contractor can begin moving a portion of the temporary cofferdam to access other areas of in-stream construction.