Visit Roanoke, VA Homepage
A photogram of a flood on Salem Avenue

Pwojè Rezistans Inondasyon Sant Vil la

The City of Roanoke is making strides to reduce downtown flooding by upgrading stormwater drainage system so it can handle more water volume.

Phase 1: 1st Street SW

Five storm drainage inlets located on 1st Street SW are going to be upsized, which will reduce flood risk in the area. The drainages are located at the intersections of 1st Street and:

  • Luck Avenue SW
  • Church Avenue SW
  • Kirk Avenue SW

The City is working with local business owners to minimize disruption as much as possible. We appreciate your patience with traffic and noise disriptions as we complete this important project that will protect life and propterty downtown.

  • Timeline: March 2026 – May 2026
  • Impacts: Expect periodic roadway, sidewalk, and parking detours and temporary closures

Phase 2: Kirk Ave SW

This phase will upsize two existing storm drainage inlets and add one new drainatge inlet. Together, these improvements will decrease flood risk in the area.

  • Timeline: May 2026 – August 2026
  • Impacts: Expect periodic roadway, sidewalk, and parking detours and temporary closures

Roanoke Stormwater main phone number: (540) 853-5900

A map showing construction locations on 1st Street SW and Kirk Ave SE

Rete enfòme

Resevwa notifikasyon sou aktivite k ap vini yo ak dènye nouvèl sou pwojè a.

Phases

Phase One: 1st Street SW

March - May 2026

Phase Two: Kirk Avenue SE

May - August 2026

Dat Enpòtan

27
okt. 2025

Sesyon Enfòmasyon 1ye Ri Sidwès

  • Kote: Biwo Devlopman Ekonomik Vil Roanoke (117 Church Ave SW)
  • Orè: 10:00 AM ak 2:00 PM