Wasena Skatepark Reconstruction

Welcoming a new era of community driven development in Roanoke, the City's Parks and Recreation Department is turning its attention towards the revitalization of the Wasena Skatepark. The awaited updates come on the heels of the critical bridge replacement project, demonstrating our commitment to enhancing and improving our public spaces for all residents.

A design-build contract has been finalized between the City of Roanoke and Pillar Design Studios for the design and construction of the $1.6 million skatepark. The City has committed $1,070,000 to the project, the City of Salem contributed $200,000, and the Town of Vinton contributed $50,000. Private community donors raised $280,000.

The skatepark will include a pump track, which is funded by those community donors and supplemented with $70,000 from the City of Roanoke.

Rendering shows Roanoke skaters utilizing features of the skatepark including the half-pipe and a hill

Stay Informed

Get notified on upcoming engagements and the latest project related news.

Project Phases

Feasibility Study Published
March 2018 - February 2019
Informational Public Meeting
November 2024
Construction
Early 2025

Project Updates

Important Dates

29
Mar 2018

Public Input Meeting

20
Nov 2024

Public Informational Meeting

The City’s Department of Parks and Recreation and representatives from Pillar Design Studios will hold an informational public meeting on Wednesday, November 20th, from 5:00 PM to 7:00PM at the Green Goat Restaurant on Wiley Drive, to share draft schematic designs for the skatepark with the community.

13
Mar 2026

Ribbon Cutting Ceremony

Join us in officially opening the Wasena Skatepark and Pump Track on March 13, at 1:30 p.m.