E. Weatherspoon Street Culvert Expansion

The project is on schedule and moving according to plan.

Crews have excavated the area and shored the slopes to ensure the area remains stable. They are currently pouring the new culvert barrel, which will sit higher than the existing barrel.

New walls will be installed on the existing culvert as part of the process.

The new floor will measure 140 feet long. The new barrel will be 10' tall by 10' wide.