Much progress has been made on the renovating the Sanford Depot. The project is on schedule to be complete in November 2025.
The following has been done:
- The crawl space encapsulation has been completed.
- The large windows at the top of the roof have been restored.
- Floor joists have been installed.
These projects are slated to be completed:
- New windows will be installed week of May 26
- Work to prepare the roof for new material is scheduled to begin week of May 26.
- Plumbing and electrical work to commence in June.