Construction Begins the Week of March 11th
Construction Begins the Week of March 11th
Terra-Turner Waterline Replacement Project
Planned location of construction and road closures for week of 3/11:
The Contractor is still planning on starting with two crews as shown on the map below. The intersection of Riverside and Sheridan Ave. will be closed and Terra/Turner will be closed to through traffic.
Crews may also be working on the shoulder of the road on Terra and Sheridan Ave. excavating services in preparation for connecting to a temporary water system.
Businesses with restricted access for the week
- Single Lane Access to be provided through closed area for:
o Easter Seals from Coffeen/Riverside/Terra initially, may switch from Avoca/Sherdan/Turner later in the week.
o Apartments at 577 Turner Lane, one lane from Coffeen/Riverside/Terra initially, may switch from Avoca/Sherdan/Turner later in the week.
- Access restricted from one direction:
o Pure Energy Fitness and businesses on Riverside and Terra Ave. will need to access from Coffeen Ave.
o Water Products & Solutions and businesses south of Riverside on Sheridan Ave. will need to access from Brundage Lane
o SWCA and business north of Riverside on Sheridan Ave. will need to access from Avoca
o Bosley Management will need to access from Avoca
Stay Informed
Get notified on upcoming engagements and the latest project related news.